This timeline estimator builds an illustrative bathroom programme from work stages and the waiting periods you enter. It separates pre-start decisions from construction and highlights plumbing changes, product cure and custom-glass delays. The November 2026 model supports planning a Newcastle enquiry; it cannot reserve trades, predict hidden damage or guarantee a completion date.
Enter the scope and known waits
Choose the room and whether fixture plumbing stays in place. Record known supply waits, required curing or testing intervals and restricted working days. If a structural change is unresolved, the tool identifies that dependency instead of producing a confident completion promise.
Your planning scenario
Choose your inputs, then use the button above. No contact details needed.
You can print the result without sharing contact details. Inputs are not stored or sent to a contractor. The final programme must be agreed against the actual products, approvals and available trades.
What is included in the base model?
| Stage | Illustrative working-day allowance | What can change it |
|---|---|---|
| Protection and strip-out | 2–3 | Access, removal scope and unexpected materials |
| Plumbing and electrical rough-in | 2–4 | Fixture moves, service access and inspection needs |
| Substrate and preparation | 2–4 | Repairs, support and the chosen assembly |
| Membrane application | 1–2 | System and area; cure is entered separately |
| Tiling and grouting | 4–7 | Format, pattern, drying and room geometry |
| Fit-off and handover work | 3–5 | Fixtures, glass, testing and defects |
These figures are transparent planning assumptions, not a measured contractor average. The base totals 14–25 working days before separately entered calendar holds. The process guide explains the stage sequence and why some tasks can overlap only after their dependencies are satisfied.
How do plumbing changes affect the estimate?
The model adds an illustrative 2–4 working days when you choose a minor fixture relocation. This is a scenario allowance, not a published trade productivity rate. Major drainage or structural changes return a request for a project-specific programme because a simple multiplier would hide too much uncertainty.
Tell the contractor whether the floor is a slab or timber if you know. Identify any upstairs room or access needed through a ceiling below. A retained toilet position can still need service renewal; moving it can change more than the plumbing visit alone.
Use the full renovation page to define the associated scope. Keep price and duration assumptions aligned in the cost calculator.
Enter product holds from actual instructions
The tool does not invent a universal membrane cure time. Enter the calendar-day hold specified for the system and conditions, including any separate testing or tile-product hold that lies on the critical sequence. If those figures are unknown, the output remains provisional and names the missing information.
Do not double-count the same wait in both a stage and a hold. For custom glass, enter only the supply wait that cannot overlap another task. The contractor should review that relationship when converting the scenario into a real programme.